Bus Service Diversion for Early Closure of Jurong West Avenue 4 for JRL Works

17 May 2024 - 31 December 2026

To facilitate construction works near the Jurong Region Line Bahar Junction station, a section of Jurong West Avenue 4 will be closed at 11:00pm daily from 17 May 2024 to 31 December 2026.

Originally planned to end after 15 October 2024, the extended arrangement till 31 October 2025 was announced by the contractor of Contract J105 on 16 Sep 2024 to facilitate structural and roofing works for the JRL station.

On 30 September 2025, the contractor announced an extension for the early closure till 31 December 2026.

Bus Stops Skipped for
Temporary Early Closure of Jurong West Avenue 4 for Jurong Region Line Works
Friday, 17 May 2024 – Thursday, 31 December 2026
11:00pm – Last Bus (Daily)

Road Name BS Code Bus Stop Description Affected Bus Service No.
Jurong West Ave 4 22341 Blk 673C 99, 193, 242
22349 Blk 734A CP
Jurong West St 72 27331 West Grove Pr Sch 99

Note: Service 242 will serve bus stop 27331 (West Grove Pr Sch) along Jurong West St 72 after loop towards Boon Lay Int.