Early Closure & Late Opening of Circle Line (Apr–May 2026)

Early Closures & Late Openings (ECLO) along the entire Circle Line (CCL), between Dhoby Ghaut / Marina Bay and HarbourFront, will take place across six weekends between 11 April 2026 and 17 May 2026.

Early Closure & Late Opening of Circle Line (Apr–May 2026)
Affected Dates Early Closure on Saturdays:
• 11, 18, 25 Apr 2026
• 2, 9, 16 May 2026
Late Opening on Sundays:
• 12, 19, 26 Apr 2026
• 3, 10, 17 May 2026
Period of closure On affected Early Closure days, train services will end at around 11:00 pm
On affected Late Opening days, train services will start at 9:00 am
Affected sector Entire Circle Line (Dhoby Ghaut/Marina Bay – HarbourFront)
Reason Systems integration testing across the entire Circle Line for Circle Line Stage 6
Alternative Transport Only on Sundays (Late Opening)
Shuttle 36: HarbourFront ↔ Bishan
Shuttle 37: Bishan ↔ Promenade
No Shuttle Buses offered during Early Closure on Saturdays

According to SMRT and LTA, these train service adjustments are needed for the final phase of testing and commissioning works needed to integrate the Circle Line Stage 6 systems with the existing CCL network.

Like the earlier early closures and late openings (Sep–Dec 2025), these service adjustments will provide the necessary engineering hours needed for safe and rigorous testing and commissioning of the train systems.

These integration tests could only be carried out after tunnel strengthening work between Mountbatten and Paya Lebar stations (Jan–Apr 2026), as these tests require the entire CCL to be operational.


Affected MRT Stations

Circle Line

As a result, CCL train services will:

  • End earlier at 11:00pm during affected Saturdays (Early Closure)
  • Start later at 9:00am during affected Sundays (Late Opening)

Shuttle Bus Services

Shuttles 36 & 37 will be provided on Late Opening days only (affected Sundays). They will operate between HarbourFront—Bishan & Bishan—Promenade respectively.

Fares for the Shuttle Bus Services are equivalent to the distance travelled by train.

Shuttle Operating Dates MRT Stations Served
Shuttle 36 All Late Opening dates:
12, 19, 26 Apr 2026
3, 10, 17 May 2026
HarbourFront, Telok Blangah, Labrador Park, Pasir Panjang, Haw Par Villa, Kent Ridge, one-north, Buona Vista, Holland Village, Farrer Road, Botanic Gardens, Caldecott, Marymount & Bishan
Shuttle 37 Bishan, Lorong Chuan, Serangoon, Bartley, Tai Seng, MacPherson, Paya Lebar, Dakota, Mountbatten, Stadium, Nicoll Highway & Promenade

Notes:

  • No shuttle services are offered between:
    Promenade – Dhoby Ghaut &
    Promenade – Marina Bay
  • No shuttle services will be provided during Early Closure.