The Bus Contracting Model (BCM), formerly known as the Government Contracting Model (GCM), is a gross-cost contracting model for public bus services in Singapore where Public Transport Operators bid for the right to operate bus routes under the Land Transport Authority.
First announced in 2014 and implemented on 1 September 2016, the BCM brought all public buses and related infrastructure under the ownership of the government. Under this model, LTA assumes the central role of planning bus services, while public transport operators bid for the right to operate the bus routes in a package.
Bus operators are paid to run bus routes according to service standards set by LTA. The competitive tendering process fosters competition in the bus industry, encouraging operators to adopt a low-cost operating model while running a reliable bus service for commuters, with financial incentives awarded based on good performance. The model also encourages operators to invest in areas like recruitment, staff training, and enhancing the professionalism of the bus workforce.
Presently, there are 14 bus packages managed by four operators in Singapore.
Overview
Under the BCM, bus operators are required to:
- Lease operating assets from the Government as specified in the awarded contract.
- Adhere to specified performance standards in operating their assigned bus services.
- Operate and maintain the leased buses and onboard equipment (e.g., fare equipment and fleet management equipment) provided by the Government.
- Operate and maintain the Bus Interchanges and new Bus Depots included in the Route Packages, along with all the equipment and systems provided within.
- Collect and enforce fares approved by the Public Transport Council for travel on the allocated Route Package Bus Services, acting on behalf of the Government.
- Provide bus service information at all bus stops and bus interchanges served by the Route Packages’ Services.
- Offer customer management services, including lost and found services, as well as a hotline for commuter feedback and inquiries.
Additionally, an Incentive Framework is established to encourage operators to deliver quality bus services to commuters and maintain the provided assets effectively. If the operator meets the standards, it can receive a performance payment of up to 10% of its annual service fee. Conversely, if the operator fails to meet the standards, up to 10% of its annual service fee may be deducted. The framework includes five performance indicators covering:
- Bus service reliability, incorporating indicators on Excess Wait Time (EWT) and On-Time Adherence (OTA) as per the Bus Service Reliability Framework.
- First and last bus punctuality to ensure accessibility for commuters.
- Maintenance of the buses provided by LTA.
- Maintenance of the Bus Interchanges and Bus Depots awarded under the Route Packages.
- Maintenance of the Bus Ticketing System.
BCM Route Packages
Bus services were consolidated into 14 route packages, each comprising approximately 300-500 buses, in August 2016. The contracts for these services are set to run for an initial five years, with the possibility of extension for another two years contingent upon satisfactory performance.
Contracts awarded from 2023 onwards allow for LTA to consider extensions ranging from two to five years after the initial five-year term.
The original inception of the Bus Contracting Model in 2014 originally planned for bus services to be divided into 12 packages.
The first three Tendered Contracts (TC) were for the Bulim, Loyang and Seletar Bus Packages, which were announced between May 2014 and June 2016. These packages were awarded to Tower Transit Singapore, Go Ahead Singapore & SBS Transit respectively, ushering in foreign operators into the local bus industry.
The remaining 11 packages were extended under Negotiated Contracts (NC) for periods ranging from 2 to 10 years, commencing from 1 September 2016. Upon the conclusion of these negotiated contracts, the bus services within these 11 packages will progressively undergo a tendering process. This phased transition approach enables LTA to refine and enhance contract management procedures, as well as the tendering and handover processes, while minimizing the risk of service disruption.
See also: Bus industry completes transition to Bus Contracting Model | Land Transport Guru
List of Bus Packages
Contract references and periods reflect the current and upcoming term(s) only.
| Package | Contract Ref | Contract Period | Incum- bent |
| Bulim Bus Package | PT217A | 29 May 2021 – 2028 (with 2 year extension) |
TTS |
| Loyang Bus Package | PT201 | 4 Sep 2016–2026 (with 2+3 year extension) |
GAS |
| Seletar Bus Package |
PT219 | 16 Mar 2025 – 2030 | SBST |
| Bukit Merah Bus Package |
PT218A | 28 Apr 2024 – 2029 | SBST |
| Sembawang–Yishun Bus Package | PT217B | 5 Sep 2021 – 2028 (with 2 year extension) |
TTS |
| Jurong West Bus Package |
PT218B | 1 Sep 2024 – 2029 | SMRT |
| Tampines Bus Package |
PT207 | Sep 2016 – Jul 2026 (with 1 year 10 months extension) |
SBST |
| PT220 | From 5 Jul 2026 | GAS | |
| Sengkang – Hougang Bus Package | PT206 | 1 Sep 2016 – 2024* (with 3 year extension; further extended for undisclosed duration) |
SBST |
| Choa Chu Kang – Bukit Panjang Bus Package | PT215 | 1 Sep 2016 – 2026 (with 3 year extension) |
SMRT |
| Woodlands Bus Package | PT216 | Sep 2016 – 2026 (with 3 year extension) |
SMRT |
| Bedok Bus Package | PT211 | Sep 2016 – 2023* (extended for undisclosed duration) |
SBST |
| Serangoon – Eunos Bus Package | PT209 | Sep 2016 – 2025* (extended for undisclosed duration) |
SBST |
| Clementi Bus Package | PT210 | Sep 2016 – 2025* (extended for undisclosed duration) |
SBST |
| Bishan – Toa Payoh Bus Package | PT208 | Sep 2016 – 2026* (extended for undisclosed duration) |
SBST |
Notes:
- Due to periodic contract extensions, the ultimate duration of many existing bus contracts may vary.
- The bus depots and bus interchanges/terminals linked with each package are subject to change, and bus services could be added or removed at LTA’s discretion.
- Service fees provided to bus operators are determined by the awarded sums announced during the contract award. These figures may be adjusted due to inflation and changes in operating mileage resulting from LTA route amendments, new bus routes, or withdrawn bus routes that affect the total mileage covered.
Timeline
Notes:
- Owing to periodic contract extensions, the final duration of many ongoing bus contracts is subject to change.
Former Bus Package Terms
| Package | Contract Ref | Contract Period | Incum- bent |
| Seletar Bus Package | PT204 | 1 Sep 2016 – 10 Mar 2018 | SBST |
| PT214 | 1 Sep 2016 – 24 Mar 2018 | SMRT | |
| PT202 | 11 Mar 2018 – 15 Mar 2025 (with 2 year extension) |
SBST | |
| Bukit Merah Bus Package | PT205 | 1 Sep 2016 – 17 Nov 2018 | SBST |
| Bulim Bus Package | PT200 | 29 May 2016 – 28 May 2021 | TTS |
| Sembawang–Yishun Bus Package | PT213 | 1 Sep 2016 – 2 Oct 2021 (with 1 year extension) |
SMRT |
| Bukit Merah Bus Package | PT203 | 18 Nov 2018 – 27 Apr 2024 (with 5 month extension) |
SBST |
| Jurong West Bus Package |
PT212 | 1 Sep 2016 – 14 Sep 2024 | SBST |
Continued on Page 2:
- Advantages of BCM
- BCM Contract Extensions
- Dual-Depot Arrangements
- New Bus Services
- Rationalisation of Bus Services
- LTA Bus Assets
- Refurbishment of Buses
- Advertising on BCM buses
- Comparison of Old and New frameworks

Sengkang-Hougang I think will stay with SBST because of the transfer of Braddell staffs over there.Most probably get extended till 2028.
Tampines I have strange instinct that either SMRT Buses or Tower Transit will bag the contract.Serangoon-Eunos probably SBST or other operator. Choa Chu Kang is not impossible goes to Go Ahead.Rest will stay with their respective operators until bidding.
Looking at the trend
2026:Tampines>>SMRT Buses Ltd.
2026/27:Choa Chu Kang–Bukit Panjang>>Go-Ahead SG Pte Ltd or new operator.
Woodlands>>SMRT Buses Ltd.
Loyang>>Go-Ahead SG Pte Ltd or new operator.
Bedok>>SBS Transit Ltd.
Serangoon–Eunos>>Tower Transit SG Pte Ltd.
Sengkang–Hougang>>SBS Transit Ltd.
2028:Clementi>>SBS Transit Ltd.
Bulim>>Tower Transit SG Pte Ltd.
Sembawang–Yishun>>Tower Transit SG Pte Ltd.
2029:Bukit Merah>>SBS Transit Ltd.
Jurong West>>SMRT Buses Ltd.
Seletar>>SBS Transit Ltd.
My predictions would be this way.
Next is the upcoming Tampines package will be retain by SBS Transit.Coming close I can think of is only Tower Transit Singapore.
Next is Bulim and Sembawang-Yishun packages with Tower Transit Singapore will definitely retain Bulim for another 5 years.
For Sembawang-Yishun maybe Transdev Asia or any other non UK euro operators is my choice.
Loyang package mostly goes to Tower Transit Singapore. Go-Ahead can kiss goodbye,Bad management especially with those ex SBST staffs there.
Choa Chu Kang–Bukit Panjang will be interesting indeed.But winner i vouch will be SBS Transit.
Next is Woodlands and the clear winner is SMRT Buses for another 5 years.
Subsequently, Serangoon-Eunos packages and SBST will retain the contract.
Sengkang-Hougang is strange but I will choose SMRT Buses to bag this.
Next is Bedok and I cannot think other than SBS Transit to win.
Move on is Clementi and I feel SMRT Buses will bag this.
Next is Bishan-Toa Payoh and the obvious winner is SBS Transit.
Seletar package will be won by Tower Transit Singapore.
Bukit Merah obviously is SBS Transit.
Last Jurong West will be win by Transdev or new non UK euro operators.
For Cross Island Line definitely will goes to SBS Transit Rail / RATP One Rail SG.
If the G opts for multi modal operators then I suggest the Bulim and Sembawang-Yishun contracts award to RATP Dev Asia and Loyang and probably one more contract to another UK bus and train operators shall they decide not to award Go-Ahead.These two operators can join operate the CRL,Seletar and Tengah Line in future.
Extension
Bedok>2023 most probably to 2028.
Tampines>2024 extend till 2026 and ongoing tender process.
Sengkang-Hougang>2024 to 2026
Serangoon-Eunos>2025 to 2027 and next year will be put for bidding.
Clementi>2025 to 2028 probably.
Bishan-Toa Payoh>2025 to 2030.